Learn About Current Projects


Public Works & Engineering Services

Long-Term Control Plan

The LTCP is a federally mandated project to separate Huntington's century-old combined sewer system. The construction route along parts of Lafontaine, Tipton, and Division streets will ultimately include complete street and sidewalk reconstruction.

- Latest LTCP info as of July 9, 2025

  • Main sewer line section from Byron to Canfield/Division is complete.
  • Tipton sewer installation continues — 4 blocks to go between Cherry and Byron!
  • Curb/sidewalk prep underway on the project’s east end.
  • Full street restoration will follow to avoid piecemeal repairs.

- Intersection Closures

  • Cherry & Tipton: Currently closed.
  • Jefferson & Tipton: Closing on or after July 14

Thanks for your continued patience as we build a better Huntington!

Division Street Reconstruction

Crews are continuing storm sewer work on Division Street to accommodate drainage and grading changes from the road's new design. This phase will continue through the week of July 7, with temporary closures of individual blocks as work progresses.

- What to Expect:

  • Sidewalks: Some sections may be removed as needed for construction and to install ADA-compliant ramps.
  • Driveways & Parking: Later in the project, access to driveways and on-street parking may be temporarily impacted. Our construction partners will coordinate directly with affected residents.

- Project Goal

This project, including work under the LTCP, will fully reconstruct Division Street between Guilford and Tipton.

Flaxmill Road Fire Station

Plans and designs are being developed to construct a new Fire Station on Flaxmill Road. If Council ultimately gives the project final approval, the new facility will replace the aging station and administrative offices on Condit Street. We're exploring potential options to accelerate the construction timeline and begin in fall 2025.

Riverfork West Industrial Park

Riverfork West is under development in partnership with Huntington United Economic Development. Teijin Automotive opened there in 2024 as the park's first tenant.

West Park Drive Reconstruction

An initial topographic survey was completed in 2024 between Victory Noll Drive and Dimond Street. The project will include reconstruction, new drainage, and trail connections with a bid expected in 2028.


Community Development & Redevelopment

H.K. Porter Brownfield Site Cleanup

Backed by a nearly $1 million federal grant, the City continues cleanup and redevelopment planning for the 12-acre H.K. Porter site. Nine companies have submitted sealed demolition bids, which were opened during the July 7 meeting of the Board of Public Works and Safety. The bids are currently under review.

Destination Downtown Master Planning

The plan was adopted by City Council on April 30, 2024. View the final draft at huntingtondowntownplan.com under "Draft Recommendations".

Little River Streambank Stabilization

A $70,000 DNR grant will fund a 2025 stabilization project for a 750-foot section of the Little River near Erie Heritage Park.


Parks & Recreation

Hayes-Lemmerz Skate Park Rebuild

Local enthusiasts and Hunger Skateparks of Bloomington are working with Parks & Recreation to redesign the aging park. A crowdsourcing fundraiser has launched on Patronicity!


Upcoming & Developing Projects

City Building Renovations

Modernizing systems and reusing space after the relocation of the police and fire departments. Last major renovations: 1989.

Downtown Activation

Improving ADA access and walkability downtown, plus upcoming resurfacing and new amenities.

Community Pool Study

Students from Rose-Hulman examined feasibility in 2024. Further planning is underway.

Sunken/Shakespeare Gardens

Enhancements for parking, accessibility, and interactive use. Invasive plant control is being evaluated.

Trail Connections

Plans to link Little River Trail to Forks of the Wabash and connect Riverfork East and West industrial parks.